Chemical Process Case Study Part 2

Another aspect to this project  was the manufacture of a stainless steel mixer tank, this would be the holding vessel to which the chemicals are mixed. After welding the tank we conducted a leak detection test before the tank left our fabrication workshop, a test certificate was then issued to the client. As the tank could not be transported with motor and shaft  in tact, this was all installed on site by our own engineers. The mixer was installed carefully onto load cells  and fixed firmly to the floor in its correct position. After the mixer was installed our site teams then installed the services which included compressed air, water lines, acid  lines, and a 200mm UPVC extraction duct. To the success of this project we are now negotiating a further two mixing stations.

No items found.
ecitb logo
iso 9001 logo
FSB Logo
Copyright © 2023 Northsound Limited.